Reported Q3 gold sales increased up to 9,506 ounces for a total of 25,484 ounces for the first nine months of the year
June 30, 2007
New expansion and improvement works were undertaken at Acari. A conical crusher is currently being installed, which should increment the processing capacity to 120 tonnes per day. A thickener is also being
built for the installation of a "Merrill Crowe" system, which should be operational during the upcoming quarter. This new system will allow increasing the efficiency and substantially speeding up the whole process of the mill. In addition, additional works are in preparation in order to increase, later on, the production which should reaches or exceeds 400 tonnes per day. Tailings will be extended as well during the forthcoming months.
March 31, 2007
Has started extension works at the Acari mill, has bought a 6’x6’ crusher and a 365 Kwh conical crusher is actually being installed with thickener for a “Merrill Crowe” mill system. With these installations, the company will be able to increase its production capacity to 120 tonnes/day. The tailings pond will also be extended during the next months.