Property NewsJune 30, 2005 The permitting approvals were expected by the end of the year. September 30, 2004 A decision was made to proceed with the East Archimedes project at the Ruby Hill mine site in Nevada. The project is an open-pit, heap leach operation exploiting the East Archimedes deposit, a deeper continuation of the ore mined previously at Ruby Hill. Construction capital is estimated at about $75 million over an expected two-year construction phase that begins once permitting is secured. The mining fleet has been ordered and permitting work is ongoing. The project has an expected life-of-mine strip ratio of 9:1 and assumes an average mining rate of 100,000 tons per day. The first gold pour is targeted for mid-2007.
|