HURDAL (NORDLI)
|
|
Key Facts
New to Company & PropertyMine?
Start Here » |
Latest Information March 31, 2006 Core drilling is progressing as planned and currently the second hole is near completion. Preliminary assays from the first hole returned values above 0.05% MoS2 cutoff, from 250 m downwards and over 0.15% MoS2 from 405 - 420 m. December 31, 2005 The first hole was at 940m and was still encountering good stockwork mineralization in less altered haplogranite. Assays pending. (Feb 14/06) September 30, 2005 A work program that incorporated 3,000 meters of core drilling from 6 holes was underway. |