No processing of ore from the Freshwater section of the Plutonic East underground mine was undertaken.
June 30, 2007
Completed development drilling of 92 RC holes for 5,388 metres and 8 diamond drill holes aggregating 330 metres in the Trout area. Mineralisation has been identified in the mafic unit and is related to quartz veining and sulphide content. Best drill results recorded being 6m (83m – 89m) @ 12.68 g/t from FRC 10422, 4m (25m-29m) @ 29.17g/t Au from FRC10484, 4m (14m-18m) @ 13.48g/t Au from FRC 10481 and 4m (67m-71m) @ 10.88g/t Au from FRC 10487.
June 30, 2006
Quarter, that mining and processing operations resulted to 30,173 tonnes at a grade of 5.73g/t gold being mined and processed. Development drilling was undertaken in the Trout area involving 94 RC holes
aggregating 8,224 m were drilled to test the continuity of the Main lode grade west of the existing pit within the $700 shell. 37 of the holes returned significant intersections of gold mineralization (>5g/t Au x m) with the most significant being 7m @ 24.73 g/t Au from 14 m in FRC10394, 2 m @ 47.18 g/t Au from 97 m in FRC10358, 2 m @ 14.84 g/t Au from 60 m in FRC10353, 2 m @ 11.72 g/tAu from 79 m in FRC10328 and 4 m @ 5.72 g/t Au from 85 m in FRC10336. Further drilling is planned.